Canton Booster Pump Station Canton, GA

New Construction

Status

Bidding Closed

Bid Date4/5/24 12:00pm

Company

...

Location

116 Brown Industrial Pkwy, Canton, GA 30114

Tentative Schedule: Projected Start 5/6/2024 with approximate completion of all scopes by 2/28/2025.

The Project generally consists of the following major items:

1. Supply and installation of a prefabricated pump station building, which will include three pumps not exceeding 50 HP, variable frequency drives (VFDs) for each pump, and all control components. The prefabricated building will be mounted on a concrete pad, provided by the Contractor.

2. Supply and installation of a 200 kW diesel backup generator, with an associated automatic transfer switch.

3. Supply and install all tie-ins of water piping and electrical utilities.

4. Demolition, removal, and disposal of all water piping and structures, as indicated on the drawings.

5. All associated civil/site work, piping, structural, electrical, and instrumentation work for the completion of the project.

6. An allowance for telemetry work by Dexter Fortson.

7. A City allowance.

Bidders shall inform themselves concerning Georgia Laws and comply with same.